Quote:
Originally Posted by yabbyman
Hello Peoples
Facility = Paper Mill / Product = Paper Roll. A 1 day run says i require 3374 but says i need a further 2408. I have 44 paper Mills (have enough ingredients for 100% Mill capacity in all owned after running facility manager) How is it possible that I can be short 2408??
Cheers
|
Hi yabbyman,
What are the figures you are quoting for? A lack of pine logs to make the paper rolls or a lack of paper rolls to use in other facilities?
You have enough pine logs to make everything in the paper mills, so it shouldn't be showing a shortage of pine logs for one 15 day fill.
If it's the paper rolls that you are running out of, that facility can only make a maximum of 84 per day. If you also have 7th Dan for the paper rolls then you will be getting a chance of up to another 48% on top of that for bonus batches which could bring the amount up to around 124 paper rolls per paper mill.
If you are running out of paper rolls, you need to have a look at how many other facilities you own that use the paper rolls to see why you are running out of them, if you are loading those facilities as well.
For example you own 39 bar supply factories. Those alone would require 7,020 paper rolls to start all the products in it that require it.
You also have a considerable amount of other facilities that are using paper rolls.